Wednesday, 31. December 2025
Highlights 2025

DB InfraGO AG
International guests visit the S4 construction site as part of the UITP Summit 2025.
Work on our S4 suburban railway line is progressing successfully. Looking back, 2025 was a year full of important milestones – in construction, planning, and public relations.
Construction Progress in Section 1
Significant progress was made in the first construction phase in 2025. At the Hasselbrook rail junction, work on the grade separation structure progressed considerably. In the northern section, the floor and walls of the future railway tunnel have already been completed using reinforced concrete. In the central section, the frame structure, which will later support the railway line running above, is under construction. An underground concrete slab has been installed here to ensure the structure will be watertight. Currently, tiebacks are being installed to guarantee structural stability.
Work has also progressed visibly in Wandsbek. The first bridge superstructures arrived at Bovestraße. These are prefabricated in the workshop and then welded together on site. Simultaneously, service walkways and central supports are being built so that the bridge can support the new S-Bahn station.
At Luetkensallee, the track work has been completed, the subsoil stabilized, and the necessary preparations made for the construction of the extended pedestrian underpass. The dismantling of the old structures is now underway, before the excavation pit is sealed in early 2026 and construction of the new frame structure begins in the spring.
The trial operation of the transparent MetaWindows continues successfully. More than 900 square meters of these transparent noise barriers have been erected since October 2024 as part of the operational testing. The analysis of the most recent inspection is currently being compiled. Preliminary results already show that the noise-absorbtion on the track side is just as effective as that of the traditional aluminum elements.

DB Engineering & Consulting GmbH
The trough of the overpass structure in Hasselbrook is clearly visible by the end of 2025.

DB InfraGO AG
The superstructures for the railway overpass on Bovestraße are arriving and are being prepared for use.

DB InfraGO AG
Luetkensallee became a construction site and soil stabilization work is in full swing.
Planning for construction phases 2 and 3 as well as for the individual measures
In the second planning approval phase, we also made significant progress in 2025. In March, the third amendment to the plans was finalized and publicly announced. Those affected by the amendment then had another opportunity to submit objections. In October, the public hearing process concluded, and the hearing report was received. This report compiles the objections thematically and categorizes them from a technical perspective. The planning approval authority uses the report as a basis for its decision on the planning approval or to identify necessary revisions to the plans.
There were also positive developments in the third planning approval phase. Practical solutions were found for issues raised in the submitted objections, and these are currently being incorporated into the planning documents. At Ahrensburg West, boreholes were drilled to examine the subsoil more closely and to prepare the geotechnical report. At Brauner Hirsch, alternatives were examined that avoid archaeologically valuable areas and thus require significantly less disturbance to the ground. The environmental documentation has also been further developed: Important information was obtained through re-mapping of fauna (wildlife) and biotopes (habitats).
Particularly pleasing: the planning approval for the individual project in Bad Oldesloe has been in place since November.
The experience gained from the construction work in Wandsbek is also providing important foundations for the upcoming construction phases. Findings from soil stabilization, bridge construction, and noise protection are being incorporated into further planning.

DB InfraGO AG
The S4 suburban railway line's booth invited you to exchange ideas at the Mobility Festival 2025!

DB InfraGO AG
Representatives of S4 in international exchange at the UITP Summit 2025 in Hamburg

DB InfraGO AG
In 2025, residents and interested parties were able to explore the S4 construction site during 3 public guided tours.

DB InfraGO AG
On Rail Day, interested parties experienced the S4 construction site up close and with bingo fun!
Public relations
2025 was also a very active year in terms of communication. Numerous visitors participated in our public construction site tours during the summer. At the UITP Summit, the S4 presented itself as a flagship project for Hamburg and also offered international guests an exclusive technical tour of the construction site. On Rail Day in September, the project team organized two special tours with an S4 bingo game – afterwards, the information train invited participants to chat over coffee and cookies.
The information train is now taking a winter break until the end of January 2026 and will then reopen with adjusted hours. Learn more about the information train here.
Further impressions and background information on the project can be found at any time in our project diary.



































































































































































































































